Sample PMP Exam

Your Personal Exam ID: 733890479 (record this on paper)
You can access this exam until: Wednesday 23rd of May 2018



Question 1:

Schedules are used in many ways. In a project to build a bridge the project manager wants to use a tool that will show the scheduled activities in such a way that it is easy to see when each activity starts and finishes and which activities are taking place at the same time. Which tool should be used?

A - PERT chart
B - Gantt chart
C - Precedence diagram
D - GERT chart