During the full life cycle of the project, a plot of the project’s expected expenditure will usually follow a characteristic “S” shape. This indicates that:

A - There is a cyclic nature to all projects
B - Problems will always occur in the execution phase
C - There are high expenditure during closeout
D - The bulk of the project budget will be spent in the execution phase